Add one lane EB SR-91 from SR-241/SR-91 to SR-71/SR-91 |
Description: In Anaheim, from Route 241 to Route 71. Provide one EB lane.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange, Riverside |
City | Anaheim, Yorba Linda |
Zip Code | 92808, 92862, 92880, 92887 |
Senate District |
29, 33, 37 |
Assembly District | 60, 71 |
Congressional District | 42, 44 |
Caltrans District |
12 |
County/State Route | Riverside 91 |
Postmile Begin/End | 0 2.9 |
County/State Route | Orange 91 |
Postmile Begin/End | 15.9 18.9 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 6216 | 6216 |
Lane Miles Added (Mixed) | 5.9 | 6 |
Peak Period Time Savings (minutes) | 495033 | 495033 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
OCTA | Rose Casey | (714) 560-5729 | rcasey@octa.net | |
Design (PS&E) Phase |
Caltrans | Adnan Maiah | (949) 724-2089 | adnan.maiah@dot.ca.gov | |
Right of Way Phase |
Caltrans | Adnan Maiah | (949) 724-2089 | adnan.maiah@dot.ca.gov | |
Construction Phase |
Caltrans | Adnan Maiah | (949) 724-2089 | adnan.maiah@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Ryan Chamberlain | (949) 724-2899 | Ryan_Chamberlain@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$71,440 | $-71,440 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $52,887 | $52,887 | ||||
Local** |
$9,060 | $-1,188 | $7,872 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $80,500 | $-19,741 | $60,759 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,700 | $244 | $1,944 | $1,945 | |||
Design(PS&E) |
$6,700 | $1,300 | $8,000 | $7,160 | |||
Right of Way |
$660 | $2,268 | $2,928 | $2,343 | |||
Construction |
$71,440 | $-23,553 | $47,887 | $44,943 | |||
Total* | $80,500 | $-19,741 | $60,759 | $56,392 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
05/01/2004 12/01/2007 |
|
05/01/2004 12/01/2007 |
100 | 05/01/2004 12/31/2007 |
0 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2007 03/01/2009 |
|
07/01/2007 03/01/2009 |
100 | 07/01/2007 05/14/2009 |
0 -2 |
|
Begin Right of Way Phase
End Right of Way Phase |
07/01/2007 03/01/2009 |
|
07/01/2007 03/01/2009 |
100 | 07/01/2008 05/14/2009 |
-12 -2 |
|
Begin Construction Phase
End Construction Phase |
08/01/2009 09/01/2011 |
|
08/01/2009 09/01/2011 |
100 | 08/29/2009 05/13/2011 |
-1 4 |
|
Begin Closeout Phase
End Closeout Phase |
09/01/2011 09/01/2015 |
|
09/01/2011 09/01/2015 |
100 | 04/01/2011 03/28/2012 |
5 42 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 05/01/2009 | 05/01/2009 | 100 | 09/01/2010 | -16 | ||
Implementation Date | 06/01/2009 | 06/01/2009 | 0 | 10/01/2010 | -16 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 6216 | 6216 |
Lane Miles Added (Mixed) | 5.9 | 6 |
Peak Period Time Savings (minutes) | 495033 | 495033 |
Bond Funding Cost | |
---|---|
Adopted: |
$71,440,000 |
Current Approved: |
$0 |
Actual Expenditures: |
$0 |
Status as of December 31, 2023.