Add one lane EB SR-91 from SR-241/SR-91 to SR-71/SR-91

Description: In Anaheim, from Route 241 to Route 71. Provide one EB lane.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange, Riverside
City Anaheim, Yorba Linda
Zip Code 92808, 92862, 92880, 92887
 
Senate District
29, 33, 37
Assembly District 60, 71
Congressional District 42, 44
 
Caltrans District
12
 
 
County/State Route Riverside 91
Postmile Begin/End 0 2.9
 
County/State Route Orange 91
Postmile Begin/End 15.9 18.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  6216    6216  
Lane Miles Added (Mixed)  5.9    6  
Peak Period Time Savings (minutes)  495033    495033  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
OCTA Rose Casey (714) 560-5729   rcasey@octa.net
Design (PS&E) Phase
Caltrans Adnan Maiah (949) 724-2089   adnan.maiah@dot.ca.gov
Right of Way Phase
Caltrans Adnan Maiah (949) 724-2089   adnan.maiah@dot.ca.gov
Construction Phase
Caltrans Adnan Maiah (949) 724-2089   adnan.maiah@dot.ca.gov
 
Corridor System Management Plan
Caltrans Ryan Chamberlain (949) 724-2899   Ryan_Chamberlain@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$71,440 $-71,440 $0
Non-bond Funding
State/Federal*
$0 $52,887 $52,887
Local**
$9,060 $-1,188 $7,872
Non Budgeted ETC
$0 $0 $0
 
Total**** $80,500 $-19,741 $60,759

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,700 $244 $1,944 $1,945
Design(PS&E)
$6,700 $1,300 $8,000 $7,160
Right of Way
$660 $2,268 $2,928 $2,343
Construction
$71,440 $-23,553 $47,887 $44,943
 
Total* $80,500 $-19,741 $60,759 $56,392

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/01/2004 

12/01/2007 
 

 
05/01/2004 

12/01/2007 
100  05/01/2004 

12/31/2007 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

03/01/2009 
 

 
07/01/2007 

03/01/2009 
100  07/01/2007 

05/14/2009 


-2 
Begin Right of Way Phase

End Right of Way Phase
07/01/2007 

03/01/2009 
 

 
07/01/2007 

03/01/2009 
100  07/01/2008 

05/14/2009 
-12 

-2 
Begin Construction Phase

End Construction Phase
08/01/2009 

09/01/2011 
 

 
08/01/2009 

09/01/2011 
100  08/29/2009 

05/13/2011 
-1 

Begin Closeout Phase

End Closeout Phase
09/01/2011 

09/01/2015 
 

 
09/01/2011 

09/01/2015 
100  04/01/2011 

03/28/2012 


42 
Corridor System Management Plan
Adoption Date 05/01/2009    05/01/2009  100  09/01/2010  -16 
Implementation Date 06/01/2009    06/01/2009  10/01/2010  -16 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 6216 6216
Lane Miles Added (Mixed) 5.9 6
Peak Period Time Savings (minutes) 495033 495033

Bond Funding Cost
Adopted:
$71,440,000
Current Approved:
$0
Actual Expenditures:
$0

 

Status as of December 31, 2023.